Q: Project Time Management What are the Project Management Processes included in the Project Time Management?

  • Show Answer
  • Workspace

Answer :
Explanation :

Activity Definition - Identifying the Specific schedule activities that need to be performed to produce the various project deliverables. Activity Sequencing - Identifying and documenting dependencies among schedule activities Activity Resource Estimating - Estimating the type and quantities of resources required to perform each schedule activity Activity Duration Estimating - Estimating the number of work periods that will be needed to complete individual schedule activities Schedule Development - Analyzing activity sequences, durations, resource requirements, and schedule constraints to creae the project schedule. Schedule Control - Controlling changes to the project schedule