Quantitative Aptitude Practice Question and Answer

Q: If J is the interest on K and K is the interest on L, the rate and time is the same on both the cases. What is the relation between J, K and L  ? 2049 0

  • 1
    J x J = KL
    Correct
    Wrong
  • 2
    K x K= JL
    Correct
    Wrong
  • 3
    L x L = JK
    Correct
    Wrong
  • 4
    JKL = 1
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 2. "K x K= JL"
Explanation :

Answer: B) K x K= JL Explanation: Let the Time be 'N' and Rate be 'R'  J = (K x NR)/100 K = (L x NR)/100  J/K = NR/100 K/L = NR/100  J/K = K/L  K x K = JL

Q: A can do a piece of work in 30 days. He works at it for 6 days and then B finishes it in 18 days. In what time can A and B together it ? 2049 0

  • 1
    14 1/2 days
    Correct
    Wrong
  • 2
    11 days
    Correct
    Wrong
  • 3
    13 1/4 days
    Correct
    Wrong
  • 4
    12 6/7 days
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 4. "12 6/7 days"
Explanation :

Answer: D) 12 6/7 days Explanation: Let 'B' alone can do the work in 'x' days 6/30 + 18/x = 1 => x = 22.5   1/30 + 1/22.5 = 7/90  => 90/7 = 12 6/7 days

Q: Which one of the following is not a prime number? 2048 0

  • 1
    91
    Correct
    Wrong
  • 2
    71
    Correct
    Wrong
  • 3
    41
    Correct
    Wrong
  • 4
    31
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 1. "91"
Explanation :

Answer: A) 91 Explanation: Prime Numbers :: Numbers which are divisible by only 1 and itself are Prime Numbers.   It's answer will be 91. Because 91 can be divisible by 7,13,91,1. It is quite clear that prime number should be divisible only by itself and by 1.

  • Show AnswerHide Answer
  • Workspace

Answer : 3. "37"
Explanation :

Answer: C) 37 Explanation: The number of liters in each can = HCF of 80, 144 and 368 = 16 liters.Number of cans of Maaza = 368/16 = 23Number of cans of Pepsi = 80/16 = 5Number of cans of Sprite = 144/16 = 9The total number of cans required = 23 + 5 + 9 = 37 cans.

Q: How many iron rods, each of length 7 mts and diameter 2 cms can be made out of 0.88 cubic metre of iron ? 2044 0

  • 1
    500
    Correct
    Wrong
  • 2
    600
    Correct
    Wrong
  • 3
    400
    Correct
    Wrong
  • 4
    300
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 3. "400"
Explanation :

Answer: C) 400 Explanation: Given length of iron rod =7 mts and  and diameter of rod = 2 cms  => r = 1/100 mts Therefore,  Volume of one rod = πr2h cu. m =  227×11002×7cu. m = 115000 cu. m Given volume of iron = 0.88 cu. m  Therefore, Number of rods = 0.88×500011 = 400.

Q: 12 students of class IX took part in GK quiz. If the number of boys is 4 more than the number of girls. Find the number of boys and girls took part in the quiz ? 2042 0

  • 1
    7, 5
    Correct
    Wrong
  • 2
    9, 3
    Correct
    Wrong
  • 3
    8, 4
    Correct
    Wrong
  • 4
    6, 6
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 3. "8, 4"
Explanation :

Answer: C) 8, 4 Explanation: Let the number of girls = x => x + x + 4 = 12 => 2x = 8 => x = 4 => Number of girls = 4 => Number of boys = 4 + 4 = 8

Q: P alone can do a piece of work in 24 days. The time taken by P to complete one-third of work is equal to time taken by Q to complete half of the work. How many days are required to complete by P and Q working together ? 2042 0

  • 1
    9 3/5 days
    Correct
    Wrong
  • 2
    7 days
    Correct
    Wrong
  • 3
    6 3/7 days
    Correct
    Wrong
  • 4
    8 days
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 1. "9 3/5 days"
Explanation :

Answer: A) 9 3/5 days Explanation: Let the total work be 'W' As per the given information, P can complete the work 'W' in 24 days. => one day work of P = W/24 And also given that, The time taken by P to complete one-third of work is equal to time taken by Q to complete half of the work => PW/3 = QW/2 => P's 1 day =    W/24    ?    =      W/3 =>  ?  = 24W/3W  = 8 => QW/2 = 8 days => Q alone can complete the work W in 16 days => P + Q can complete the work in 1/24 + 1/16 = 5/48 => 48/5 days = 9 3/5 days.

Q: Write 0.125 as a percent %? 2041 0

  • 1
    12%
    Correct
    Wrong
  • 2
    12.5%
    Correct
    Wrong
  • 3
    13%
    Correct
    Wrong
  • 4
    13.5%
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 2. "12.5%"
Explanation :

Answer: B) 12.5% Explanation: Here to convert 0.125 into % First convert to fractio Multiply and divide by 1000 => 0.125 x 10001000 = 1251000 = 18 => Now, in percentage18 x 100 = 12.5%

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully