Q: A take twice as much time as B or thrice as much time to finish a piece of work. Working together, they can finish the work in 2 days. B can do the work alone in ? 1799 0

  • 1
    3 hrs
    Correct
    Wrong
  • 2
    6 hrs
    Correct
    Wrong
  • 3
    7 hrs
    Correct
    Wrong
  • 4
    5 hrs
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 2. "6 hrs"
Explanation :

Answer: B) 6 hrs Explanation: Suppose A, B and C take x, x/2 and x/3 respectively to finish the work. Then, (1/x + 2/x + 3/x) = 1/2 6/x = 1/2 => x = 12 So, B takes 6 hours to finish the work.

Q: In how many ways can letter of the word RAILINGS arrange so that R and S always come together? 1799 0

  • 1
    1260
    Correct
    Wrong
  • 2
    2520
    Correct
    Wrong
  • 3
    5040
    Correct
    Wrong
  • 4
    1080
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 3. "5040"
Explanation :

Answer: C) 5040 Explanation: The number of ways in which the letters of the word RAILINGS can be arranged such that R & S always come together is   Count R & S as only 1 space or letter so that RS or SR can be arranged => 7! x 2!   But in the word RAILINGS, I repeated for 2 times => 7! x 2!/2! = 7! ways = 5040 ways.

Q: A woman fills a bucket in 6 minutes. 1845 buckets have to be filled from 8 am. to 9:30 am. How many woman employees should be employed for this task? 1798 0

  • 1
    111
    Correct
    Wrong
  • 2
    117
    Correct
    Wrong
  • 3
    123
    Correct
    Wrong
  • 4
    139
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 3. "123"
Explanation :

Answer: C) 123 Explanation: We know that, M1 × D1W1 = M2 × D2W2 Here M1 = 1, D1 = 6 min, W1 = 1 and M2 = M, D2 = 90 min, W2 = 1845   1 × 61 = M × 901845  => M = 123

Q: The length of a brigade which a train 130 m long and traveling at 45kmph can cross in 30 seconds, is 1797 0

  • 1
    196 mts
    Correct
    Wrong
  • 2
    220 mts
    Correct
    Wrong
  • 3
    230 mts
    Correct
    Wrong
  • 4
    245 mts
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 4. "245 mts"
Explanation :

Answer: D) 245 mts Explanation: Let the length of the brigade is x mtsThen Distance = 130 + x mtsgiven speed = 45 kmph = 45 x5/18 m/sTime = 30 secT = D/S => 30 = 130+x/(45x5/18)=> x = 245 mts.

Q: Priya can do a work in 16 days. In how many days will the work be completed by Sai, if the efficiency of Sai is 60% more than that of Priya ? 1796 0

  • 1
    8 days
    Correct
    Wrong
  • 2
    12 days
    Correct
    Wrong
  • 3
    14 days
    Correct
    Wrong
  • 4
    10 days
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 4. "10 days"
Explanation :

Answer: D) 10 days Explanation: Ratio of efficiencies of Priya and Sai is Sai : Priya = 160 : 100 = 8 : 5 Given Priya completes the work in 16 days Let number of days Sai completes the work be 'd' => 5×16 = 8×d d = 10 days. Therefore, number of days Sai completes the work is 10 days.

Q: In what time a 360 m. long train moving at the speed of 44 km/hr will cross a 140 m. long bridge ? 1794 0

  • 1
    36 sec
    Correct
    Wrong
  • 2
    39 sec
    Correct
    Wrong
  • 3
    41 sec
    Correct
    Wrong
  • 4
    43 sec
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 3. "41 sec"
Explanation :

Answer: C) 41 sec Explanation: Speed = 44 kmph x 5/18 = 110/9 m/s We know that, Time = distance/speed Time = (360 + 140) / (110/9) = 500 x 9/110 = 41 sec.

Q: A motorboat running upstream takes 8 hours 48 minutes to cover a certain distance, while it takes 4 hours to cover the same distance running downstream. What is the ratio between the speed of the motorboat and speed of the water current respectively? 1793 0

  • 1
    3:7
    Correct
    Wrong
  • 2
    7:9
    Correct
    Wrong
  • 3
    5:4
    Correct
    Wrong
  • 4
    8:3
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 4. "8:3"
Explanation :

Answer: D) 8:3 Explanation: Let the man's rate upstream be x kmph and that downstream be y kmph. Then, distance covered upstream in 8 hrs 48 min = Distance covered downstream in 4 hrs. x x 8 4 = (y x 4) 5 44 x =4y 5  y = 11 x. 5  Required ratio = y + x : y - x 2 2    = 16x x 1 : 6x x 1 5 2 5 2    = 8 : 3 5 5    = 8 : 3.

Q: It was Tuesday on Jan 1, 2006. What was the day of the week Jan 1, 2010 ? 1791 0

  • 1
    Sunday
    Correct
    Wrong
  • 2
    Friday
    Correct
    Wrong
  • 3
    Monday
    Correct
    Wrong
  • 4
    Tuesday
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 2. "Friday"
Explanation :

Answer: B) Friday Explanation: On 31st December, 2005 it was Monday. Number of odd days from the year 2006 to the year 2009 = (1 + 1 + 2 + 1) = 5 days. On 31st December 2009, it was Thursday. Thus, on 1st Jan, 2010 it is Friday.

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully