Bank Exams Practice Question and Answer

  • Show AnswerHide Answer
  • Workspace

Answer :
Explanation :

Q(f)      -     O(m)  (Tennis)      (Basketball)               |              R(m)  -   N(f)             (Golf)     (Hockey)                       |                M              P(m)         (Cricketer)      (Football)   Answer   1: Can't be determined because M may be Grandson or Grand daughter of Q. Answer   2: Q plays Tennis.

Q: As per the policies of the Government of India any proposal for FDI in single brand retail should not be above line of ___ 934 0

  • 1
    33%
    Correct
    Wrong
  • 2
    43%
    Correct
    Wrong
  • 3
    48%
    Correct
    Wrong
  • 4
    51%
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 4. "51%"
Explanation :

Answer: D) 51% Explanation:

Q: Which of the following is a Composite number? 920 0

  • 1
    0
    Correct
    Wrong
  • 2
    19
    Correct
    Wrong
  • 3
    29
    Correct
    Wrong
  • 4
    91
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 4. "91"
Explanation :

Answer: D) 91 Explanation: Here in the given numbers 91 is a Composite number. Since it has factors of 7 and 13 other than 1 and itself.   Composite Numbers : A composite number is a positive integer which is not prime (i.e., which has factors other than 1 and itself). Examples :: 4, 6, 8, 12, 14, 15, 18, 20, ...

Q: A person can row 8 1/2 km an hour in still water and he finds that it takes him twice as long to row up as to row down the river. The speed of the stream ? 918 0

  • 1
    1.78 kmph
    Correct
    Wrong
  • 2
    2.35 kmph
    Correct
    Wrong
  • 3
    2.83 kmph
    Correct
    Wrong
  • 4
    3.15 kmph
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 3. "2.83 kmph"
Explanation :

Answer: C) 2.83 kmph Explanation: Given speed of the person = 8 1/2 = 17/2 kmphLet the speed of the stream = x kmphspeed of upstream = 17/2 - xspeed of downstream = 17/2 + xBut given that,2(17/2 - x) = 17/2 + x=> 3x = 17/2=> x = 2.83 kmph.

Q: What is the name of the Indian Coast Guard Ship which has been decommissioned by the Indian navy recently ? 909 0

  • 1
    Sarathi
    Correct
    Wrong
  • 2
    Shaurya
    Correct
    Wrong
  • 3
    Varuna
    Correct
    Wrong
  • 4
    Ayush
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 3. "Varuna"
Explanation :

Answer: C) Varuna Explanation:

Q: Which Color has the Longest Wavelength? 901 0

  • 1
    Violet
    Correct
    Wrong
  • 2
    Yellow
    Correct
    Wrong
  • 3
    Red
    Correct
    Wrong
  • 4
    White
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 3. "Red"
Explanation :

Answer: C) Red Explanation: The visible colors from Longest wavelength to Shortest wavelength are :: Red, Orange, Yellow, Green, Blue and Violet.                     Red > Orange > Yellow > Green > Blue > Violet.   1. Infrared radiation has a longer wavelength than visible Red light.   2. Ultraviolet radiation has a shorter wavelength than the visible violet light.    3. The white light is a mixture of the colors of the visible spectrum.

Q: What is CPC  ? 898 0

  • 1
    Central Person scheme
    Correct
    Wrong
  • 2
    Central Pay commission
    Correct
    Wrong
  • 3
    Central Paid determination
    Correct
    Wrong
  • 4
    Central Pay scheme
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 2. "Central Pay commission"
Explanation :

Answer: B) Central Pay commission Explanation:

Q: A can complete a work in 12 days with a working of 8 hours per day. B can complete the same work in 8 days when working 10 hours a day. If A and B work together, working 8 hours a day, the work can be completed in --- days  ? 886 0

  • 1
    51/24
    Correct
    Wrong
  • 2
    87/5
    Correct
    Wrong
  • 3
    57/12
    Correct
    Wrong
  • 4
    60/11
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 4. "60/11"
Explanation :

Answer: D) 60/11 Explanation: A can complete the work in 12 days working 8 hours a day => Number of hours A can complete the work = 12×8 = 96 hours  => Work done by A in 1 hour = 1/96   B can complete the work in 8 days working 10 hours a day => Number of hours B can complete the work = 8×10 = 80 hours  => Work done by B in 1 hour = 1/80   Work done by A and B in 1 hour = 1/96 + 1/80 = 11/480  => A and B can complete the work in 480/11 hours   A and B works 8 hours a day. Hence total days to complete the work with A and B working together  = (480/11)/ (8) = 60/11 days

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully