Answer : 4. "DMcGregor's X Theory"
Explanation :

Answer: D) DMcGregor's X Theory Explanation: Answer A is incorrect because Meridith and Mann did not develop an autocratic management theory.Answer B is incorrect because Deming's theories did not involve any of the X and Y theories that were developed by McGregor. Answer C is incorrect because Earned value is not related to X or Y management theories.

Q: Management by projects views aspects of ongoing operations as projects in order to apply Project Management techniques to them. This can be used to describe an oranizational approach to the management of ongoing operations. Why would a company want to utilize this methodology on nonprojects? 1318 0

  • 1
    To keep project managers employed
    Correct
    Wrong
  • 2
    To provide better estimates about durations
    Correct
    Wrong
  • 3
    To allow the utilization of PM tools, such as earned value, to calculate ROI
    Correct
    Wrong
  • 4
    To specify the different phases within the operations
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 3. "To allow the utilization of PM tools, such as earned value, to calculate ROI"
Explanation :

Answer: C) To allow the utilization of PM tools, such as earned value, to calculate ROI Explanation: Answer A is incorrect because project managers are not effectively utilized if they are always scheduling and coordinating resources for daily operations. Answer B is incorrect because project managers are not the best resource for providing estimates on daily operations and time allocations;people doing the actual work are the best resources. Answer D is incorrect because you do not specify different phases of ongoing operations.

Q: The project life cycle can be broken into five phases that tend to overlap with each other frm one phase to another;however ,the control phase does not overlap with a specific phase. why? 1471 0

  • 1
    Change control management is seperate from the other phases
    Correct
    Wrong
  • 2
    Change control management has a plan that can be usede throughout the initiation, planning, execution, and closeout of the project
    Correct
    Wrong
  • 3
    Because the project sponsor is responsible for change control management , the project manager is not involved with that phase of the project
    Correct
    Wrong
  • 4
    Change control extends throughout the entire project from initiation to closeout
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 4. "Change control extends throughout the entire project from initiation to closeout"
Explanation :

Answer: D) Change control extends throughout the entire project from initiation to closeout Explanation: Change control management is utilized from the begining to the end of the project in order to keep it focused with an emphasis on the time and budget. Answer A is incorrect because change control management is not seperate from the other phases. Answer B is incorrect because the control plan must be throughout the other phases of a project. Its usage is not optional, and consistent utilization is imperative to managing scope creep and other scope expansions. Answer C is incorrect because the project sponsors is generally not responsible for the change control documentation, although it should be involved in the buy-in and approval process.

Q: The software development life cycle begins with a proof of concept and progress into the build, test, and acceptance phases as the project develops. Some times, differences between stakeholders can develop into conflict, which impacts the customer. As a trained, professional project manager, how do you handle this situation and resolve the customer's concerns? 1549 0

  • 1
    Let the customer vent and take notes
    Correct
    Wrong
  • 2
    Schedule a meeting
    Correct
    Wrong
  • 3
    Develope a change request for the customer
    Correct
    Wrong
  • 4
    Resolve the matter in favour of the customer
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 4. "Resolve the matter in favour of the customer"
Explanation :

Answer: D) Resolve the matter in favour of the customer Explanation:

Q: You have started your own company based upon PMI methodologies and have been contracted by the government to develope a new interface for one of its computer applications. You develope a solution and win the bid for the contract but encounter problems at the end of the project when the customer says that you did not fullfill their needs. You are throughly shocked. What is your conclusion of the situation? 1246 0

  • 1
    There are always more customers available
    Correct
    Wrong
  • 2
    If the customer is not satisfied, the project is not successful
    Correct
    Wrong
  • 3
    Change control management was not effective
    Correct
    Wrong
  • 4
    The customer did not communicate very well
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 2. "If the customer is not satisfied, the project is not successful"
Explanation :

Answer: B) If the customer is not satisfied, the project is not successful Explanation: Answer A is incorrect because without satisfied customers, we do not have potential for new projects. Answer C is incorrect because the change control management process would have likely resolved this problem. Answer D is incorrect because it is the project manager's responsibility to seek communication with the customer to set realistic expectations.

Q: One of the goals of management by objectives (MBO) is to ensure that objectives of one level within an organization are supportive of and aligned with the objectives of another level of the organization. This methodology has been popular within some organizations as they define their culture. Which of the following is not true about MBO? 1384 0

  • 1
    It has a top-down orientation
    Correct
    Wrong
  • 2
    Corrective actions are not part of the process
    Correct
    Wrong
  • 3
    You need to establish clear and achievable objectives
    Correct
    Wrong
  • 4
    MBO is a natural fit for Project Management
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 2. "Corrective actions are not part of the process"
Explanation :

Answer: B) Corrective actions are not part of the process Explanation: Corrective actions are part of the process after establishing objectives and checking on the objectives. The next step is to take corrective actions. Answers A, C, D are true statements and therfore are incorrect for this question.

  • Show AnswerHide Answer
  • Workspace

Answer : 3. "5 years"
Explanation :

Answer: C) 5 years Explanation: The payback period is how long it takes to recoup your investment. In this example, the cost was $4,000,000 and the savings was $800,000 per year. $4,000,000/$800,000 = 5. Therefore, Answer A, B and D are incorrect.

Q: Sometimes project managers forget all of the expenses that they can incur on a project, such as capital resources and assets. This can have an impact upon their budgets and the economic return on the project. A cost that has been incurred and cannot be reversed is known as a 1207 0

  • 1
    Fixed Cost
    Correct
    Wrong
  • 2
    Direct Cost
    Correct
    Wrong
  • 3
    Variable Cost
    Correct
    Wrong
  • 4
    Sunk Cost
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 4. "Sunk Cost"
Explanation :

Answer: D) Sunk Cost Explanation: Answer D is correct because a sunk cost is a project expense that will eventualy need to be paid. Answer A is incorrect because a fixed cost remains constant, regardless of any change in a company's activity. Answer B is incorrect because direct cost can be directly linked to producing specific goods or services. Answer C is incorrect because a variable cost changes in proportion to a change in the company's activity or business.

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully