Join Examsbook
651 0

Q: Project Integration Management - Processes Describe the Inputs, Tools and Techniques, Outputs of Close project Phase?

  • Show AnswerHide Answer
  • Workspace

Answer :
Explanation :

I. Inputs Project management plan Contract documentation Enterprise environmental factors Organizational process assets Work performance information Deliverables II. Tools and Techniques Project management methodology Project management information system Expert Judgment III. Outputs Administrative closure procedure Contract closure procedure Final product, service, or result Organisational process assets (updates)

Are you sure

  Report Error

Please Enter Message
Error Reported Successfully