Q: Project Time Management - Processes Describe the Inputs, Tools and Techniques, Outputs of Activity Duration Estimating ?

  • Show AnswerHide Answer
  • Workspace

Answer :
Explanation :

I. Inputs Enterprise environmental factors Organizational process assets Project scope statement Activity list Activity attributes Activity resource requirements Resource calendars Project management plan                - Risk register                - Activity cost estimates II. Tools and Techniques Expert judgment Analogous  estimating Parametric estimating Three-point estimates  Reserve analysis III. Outputs Activity duration estimates Activity attributes (updates)