Time and Work Questions Practice Question and Answer

Q: A man a woman and a boy can complete a job in 3, 4 and 12 days. How many boys must assist 1 man and 1 woman to complete the job in $$ {1\over 4} \ days$$ of a day ? 928 0

  • 1
    1
    Correct
    Wrong
  • 2
    4
    Correct
    Wrong
  • 3
    19
    Correct
    Wrong
  • 4
    41
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 4. "41"

Q: A, B and C can complete a piece of work in 24, 6 and 12 days respectively. Working together, they will complete the same work in 927 0

  • 1
    $${1\over 4}days$$
    Correct
    Wrong
  • 2
    $${7\over 24}days$$
    Correct
    Wrong
  • 3
    $$3{3\over 7}days$$
    Correct
    Wrong
  • 4
    $$4 \ days$$
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 3. " $$3{3\over 7}days$$"

Q: A can do a piece of work in 15 days and B in 20 days. If they together work it for 4 days, then the fraction of the work that is left is: 1087 0

  • 1
    $${8\over 15}$$
    Correct
    Wrong
  • 2
    $${7\over 15}$$
    Correct
    Wrong
  • 3
    $${1\over 4}$$
    Correct
    Wrong
  • 4
    $${1\over 10}$$
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 1. "$${8\over 15}$$"

Q: A can finish a piece of work in 18 days and B can do the same work in half the time taken by A. Then working together. What part of the same work they an finish in a day? 955 0

  • 1
    $${1\over 6}$$
    Correct
    Wrong
  • 2
    $${2\over 5}$$
    Correct
    Wrong
  • 3
    $${1\over 9}$$
    Correct
    Wrong
  • 4
    $${2\over 7}$$
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 1. " $${1\over 6}$$"

Q: A and B can do a piece of work in 12 days. B and C in 15 days and C and A in 20 days. If A, B and C work together, they will completer the work in : 982 0

  • 1
    5 days
    Correct
    Wrong
  • 2
    $$ 7{5\over 6} \ days$$
    Correct
    Wrong
  • 3
    10 days
    Correct
    Wrong
  • 4
    $$ 15 {2\over 3} \ days$$
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 3. " 10 days"

Q: A can do a piece of work in 6 days and B in 9 days. How many days will both take together to complete the work? 1096 0

  • 1
    7.5 days
    Correct
    Wrong
  • 2
    5.4 days
    Correct
    Wrong
  • 3
    3.6 days
    Correct
    Wrong
  • 4
    3 days
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 3. " 3.6 days"

Q: A can cultivate $${2\over 5}$$ of a land in 6 days and b can cultivate $${1\over 6}$$ of the same land in 10 days. Working together A and B can cultivate $${4\over 5}$$ of the land in; 1202 0

  • 1
    4 days
    Correct
    Wrong
  • 2
    5 days
    Correct
    Wrong
  • 3
    8 days
    Correct
    Wrong
  • 4
    10 days
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 3. " 8 days"

Q: A and B can do a piece of work in 72 days. B and C can do it in 120 days. A and C can do it in 90 days. In how many days all three together can do the work ? 1089 0

  • 1
    80 days
    Correct
    Wrong
  • 2
    100 days
    Correct
    Wrong
  • 3
    60 days
    Correct
    Wrong
  • 4
    150 days
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 3. " 60 days"

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully