Time and work Practice Question and Answer

Q:

Lal Babu and Mangallu can finish a work in 10 days while Lal Babu alone can finish that work in 15 days, then how many days will Mangallu take to do that work?

1185 0

  • 1
    30 days
    Correct
    Wrong
  • 2
    829 days
    Correct
    Wrong
  • 3
    52 days
    Correct
    Wrong
  • 4
    21 days
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 1. "30 days "

Q:

A, B and C can do a piece of work in 15 days. B and C can complete the work in 20 days. In how many days can A alone complete the work?

758 0

  • 1
    40
    Correct
    Wrong
  • 2
    60
    Correct
    Wrong
  • 3
    45
    Correct
    Wrong
  • 4
    75
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 2. "60"

Q:

If the efficiency of Q increases by $$ {33{1\over 3}{\%}}$$ and P and Q start to work together, while at the same time R starts destroying the work. Find in how many days work will be completed.

750 0

  • 1
    36 days
    Correct
    Wrong
  • 2
    48 days
    Correct
    Wrong
  • 3
    32 days
    Correct
    Wrong
  • 4
    28 days
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 1. "36 days"

  • Show AnswerHide Answer
  • Workspace

Answer : 4. "8 days"

Q:

A can do a piece of work in 24 day, B in 32 days and C in 64 days. All begin to do it together, but A leaves after 6 days and B leaves 6 days before the completion of the work. How many days did the work last?

999 0

  • 1
    15
    Correct
    Wrong
  • 2
    20
    Correct
    Wrong
  • 3
    18
    Correct
    Wrong
  • 4
    30
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 2. "20"

Q:

P, Q, R are employed to do a work for Rs. 5750. P and Q together finished 19/23 of work and Q and R together finished 8/23 of work. Wage of Q, in rupees, is-

1126 0

  • 1
    2850
    Correct
    Wrong
  • 2
    3750
    Correct
    Wrong
  • 3
    2750
    Correct
    Wrong
  • 4
    1000
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 4. "1000"

Q:

A is 50% more efficient than B. They together start the work and $$ {7\over 12}$$ th of work is left after 8 days. Find in what time B alone will complete the whole work.

767 0

  • 1
    36 days
    Correct
    Wrong
  • 2
    44 days
    Correct
    Wrong
  • 3
    48 days
    Correct
    Wrong
  • 4
    40 days
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 3. "48 days"

  • Show AnswerHide Answer
  • Workspace

Answer : 4. "24"

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully