Time and work Practice Question and Answer

Q:

If 12 men can do a piece of work in 24 days, then in how many days can 18 men do the same work?

1469 0

  • 1
    36
    Correct
    Wrong
  • 2
    20
    Correct
    Wrong
  • 3
    18
    Correct
    Wrong
  • 4
    16
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 4. "16"

Q:

A work is done by three person A, B and C. A alone takes 10 hours to complete the work but B and C working together takes 4 hours, for the completion of the same work. If all of them worked together and completed 14 times of the work, then how many hours have they worked?

1467 0

  • 1
    42 hr
    Correct
    Wrong
  • 2
    28 hr
    Correct
    Wrong
  • 3
    40 hr
    Correct
    Wrong
  • 4
    20 hr
    Correct
    Wrong
  • 5
    45 hr
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 3. "40 hr "

Q:

28 men can complete a piece of work in 15 days and 15 women can completed the same piece of work in 24 days. What is the respective ratio between the amount of work done by 30 men in 1 day and the amount of work done by 18 women in 1 days? 

1466 0

  • 1
    10 : 7
    Correct
    Wrong
  • 2
    3 : 5
    Correct
    Wrong
  • 3
    5 : 4
    Correct
    Wrong
  • 4
    9 : 5
    Correct
    Wrong
  • 5
    Not
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 1. "10 : 7 "

Q: A and B can do a piece of work in 10 days, B and C in 15 days and C and A in 20 days, C alone can do the work in : 1466 0

  • 1
    60 days
    Correct
    Wrong
  • 2
    120 days
    Correct
    Wrong
  • 3
    80 days
    Correct
    Wrong
  • 4
    30 days
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 2. " 120 days"

Q: A can finish a piece of work in 18 days and B can do the same work in half the time taken by A. Then working together. What part of the same work they an finish in a day? 1451 0

  • 1
    $${1\over 6}$$
    Correct
    Wrong
  • 2
    $${2\over 5}$$
    Correct
    Wrong
  • 3
    $${1\over 9}$$
    Correct
    Wrong
  • 4
    $${2\over 7}$$
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 1. " $${1\over 6}$$"

  • Show AnswerHide Answer
  • Workspace

Answer : 3. "35"

Q:

Ramesh can do a work in 21 days and Mahesh in 42 days. If they work on it together for 7 days, then what fraction of work is left?

1441 0

  • 1
    $$ {1\over5}$$
    Correct
    Wrong
  • 2
    $$ {1\over4}$$
    Correct
    Wrong
  • 3
    $$ {1\over2}$$
    Correct
    Wrong
  • 4
    $$ {2\over3}$$
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 3. "$$ {1\over2}$$"

Q:

10 men can complete a piece of work in 15 days. They started work and after five days 10 women joined them and the work has finished in next 5 days. In how many days can 25 women finish the same piece of work?

1438 0

  • 1
    4 days
    Correct
    Wrong
  • 2
    5 days
    Correct
    Wrong
  • 3
    6 days
    Correct
    Wrong
  • 4
    8 days
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 3. "6 days"

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully