Q:

10 men can finish painting a wall in 8 days. How many more men will be needed if the painting work is to be finished in 4 days?

1123 0

  • 1
    8
    Correct
    Wrong
  • 2
    5
    Correct
    Wrong
  • 3
    10
    Correct
    Wrong
  • 4
    20
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 3. "10"

Q:

A can do $$ {4\over 5}$$ of a work in 20 days and B can do $$ {3\over 4}$$ of the same work in 15 days. They work together for 10 days. C alone completes the remaining work in 1 day.  B and C together can complete of $$ {3\over 4}$$ of the same work in:

1122 0

  • 1
    6 days
    Correct
    Wrong
  • 2
    8 days
    Correct
    Wrong
  • 3
    5 days
    Correct
    Wrong
  • 4
    4 days
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 3. "5 days"

  • Show AnswerHide Answer
  • Workspace

Answer : 3. "25"

Q:

A can do a work alone in 30 days. He left after doing half the work. If B alone can complete the entire work in 16 days, then how many days will B take to complete the remaining work?

1121 0

  • 1
    9
    Correct
    Wrong
  • 2
    6
    Correct
    Wrong
  • 3
    8
    Correct
    Wrong
  • 4
    12
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 3. "8"

Q:

A contractor undertakes to finish a certain work in 124 days and employed 120 men. After 64 days, he found that he had already done 2/3 of the work. How many men can be discharged so that the work may finish in time ?

1118 0

  • 1
    50
    Correct
    Wrong
  • 2
    48
    Correct
    Wrong
  • 3
    56
    Correct
    Wrong
  • 4
    64
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 3. "56 "

Q:

P, Q, R are employed to do a work for Rs. 5750. P and Q together finished 19/23 of work and Q and R together finished 8/23 of work. Wage of Q, in rupees, is-

1117 0

  • 1
    2850
    Correct
    Wrong
  • 2
    3750
    Correct
    Wrong
  • 3
    2750
    Correct
    Wrong
  • 4
    1000
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 4. "1000"

Q:

A and B together can complete a work in 21 days. If A takes 42 days to complete the work alone, how many days will B take to complete the same work alone?

1116 0

  • 1
    32
    Correct
    Wrong
  • 2
    42
    Correct
    Wrong
  • 3
    27
    Correct
    Wrong
  • 4
    36
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 2. "42"

Q:

Mahadev covered some distance at some speed. If he traveled a distance of 3 km / h more, it took him 40 minutes less time. If he had covered the distance at a speed of 2 km / h less, he would have taken 40 minutes more. The distance (in km) is

1116 0

  • 1
    $$ {36{2\over3}}$$
    Correct
    Wrong
  • 2
    40
    Correct
    Wrong
  • 3
    20
    Correct
    Wrong
  • 4
    48
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 2. "40"

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully