Time and work Practice Question and Answer

Q:

P can complete a piece of work in thrice the time taken to complete Q and R together. If P and Q together can complete the work in 9 3/5 days and R alone complete in 16 days, then find the no of days taken to complete the work by P alone?

939 0

  • 1
    8
    Correct
    Wrong
  • 2
    12
    Correct
    Wrong
  • 3
    16
    Correct
    Wrong
  • 4
    24
    Correct
    Wrong
  • 5
    15
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 4. "24"

Q:

A can do a piece of work in 18 days and B in 36 days. If they work together for 9 days, then what percentage of work will be left?

931 0

  • 1
    33.3
    Correct
    Wrong
  • 2
    20
    Correct
    Wrong
  • 3
    25
    Correct
    Wrong
  • 4
    36
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 3. "25"

Q:

Amar can do a piece of work in 30 days and Raman can do the same work in 15 days. If both work together, then what percent of the total work will be completed in 4 days?

928 0

  • 1
    15
    Correct
    Wrong
  • 2
    37
    Correct
    Wrong
  • 3
    40
    Correct
    Wrong
  • 4
    45
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 3. "40"

Q:

P can do $${1\over 2} $$ of a work in 10 days and Q can do $${1\over 5}$$of the same work in 4 days. In how many days can both finish the work, working together?

924 0

  • 1
    14 days
    Correct
    Wrong
  • 2
    10 days
    Correct
    Wrong
  • 3
    15 days
    Correct
    Wrong
  • 4
    5 days
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 2. "10 days"

Q:

Aman and Raman together can complete a work in 30 days, Raman and Manan can complete the same work in 36 days and Manan and Aman can complete the same work in 45 days. In how many days can all three together complete the work?

923 0

  • 1
    12
    Correct
    Wrong
  • 2
    32
    Correct
    Wrong
  • 3
    24
    Correct
    Wrong
  • 4
    55
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 3. "24"

Q:

The rates of working of A and B are in the ratio of 2 : 3. The number of days taken by each of them to finish the work is in the ratio : 

922 0

  • 1
    3 : 2
    Correct
    Wrong
  • 2
    9 : 4
    Correct
    Wrong
  • 3
    2 : 3
    Correct
    Wrong
  • 4
    4 : 9
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 1. "3 : 2 "

Q:

P, Q and R gets a total wage of Rs.3600 if they work together. P and Q gets a total wage of Rs. 2800 if they work together and P alone gets Rs.1600. Find the efficiency ratio of P, Q and R  

920 0

  • 1
    1:2:3
    Correct
    Wrong
  • 2
    2:4:3
    Correct
    Wrong
  • 3
    4:3:2
    Correct
    Wrong
  • 4
    2:5:4
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 3. "4:3:2"

  • Show AnswerHide Answer
  • Workspace

Answer : 3. "$$25{2\over 3}$$"

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully