Time and work Practice Question and Answer
8 Q: Some men can do a piece of work in 60 days. If there are 8 more men, the work can be completed in 10 days less. What was the number of men in the beginning?
913 06321acdb69fe1d77bc0257c0
6321acdb69fe1d77bc0257c0- 130false
- 240true
- 332false
- 436false
- Show AnswerHide Answer
- Workspace
- SingleChoice
Answer : 2. "40"
Q:Answer the following questions
P, Q and R alone can complete a piece of work in 24, 36 and 18 days respectively. P started working, after 2 days R joins with them and Q joins with them after another 2 days, then find the no of days P, Q and R worked together.
913 063bd571174eba5069d4a3d46
63bd571174eba5069d4a3d46- 1$$ {5{2\over 9}\ days}$$false
- 2$$ {6{2\over 9}\ days}$$true
- 3$$ {4{3\over 5}\ days}$$false
- 4None of thesefalse
- Show AnswerHide Answer
- Workspace
- SingleChoice
Answer : 2. "$$ {6{2\over 9}\ days}$$"
Q: A work can be completed by 20 men in 50 days. 30 more men join them after 10 days of work. How many days will be saved in completion of the work?
901 06433db38a16c2dfa9cdb03f3
6433db38a16c2dfa9cdb03f3- 118 daysfalse
- 220 daysfalse
- 324 daystrue
- 428 daysfalse
- Show AnswerHide Answer
- Workspace
- SingleChoice
Answer : 3. "24 days"
Q: A is as efficient as B and C together. Working together A and B can complete a work in 36 days and C alone can complete it in 60 days. A and C work together for 10 days. B alone will complete the remaining work in:
899 064f84e4f6e0e55b91d9bfc19
64f84e4f6e0e55b91d9bfc19- 188 daysfalse
- 2110 daystrue
- 384 daysfalse
- 490 daysfalse
- 540 daysfalse
- Show AnswerHide Answer
- Workspace
- SingleChoice
Answer : 2. "110 days"
Q: A can do a piece of work alone in 30 days. B is 25% less efficient than A, while C is $$33{1\over 3}$$ % more efficient than B. In how many days can A, B and C, working together, complete the work?
886 0642d31969d18d2e8ae2a70d6
642d31969d18d2e8ae2a70d6- 1$${150\over 11}$$ daysfalse
- 2$${120\over 11}$$ daystrue
- 3$${140\over 11}$$ daysfalse
- 4$${130\over 11}$$ daysfalse
- Show AnswerHide Answer
- Workspace
- SingleChoice
Answer : 2. "$${120\over 11}$$ days"
Q: A and B together can do a piece of work in 12 days, A and C together can do the same work in 15 days. If B and C together can do the same work in 20 days, then in how many days A, B and C together can complete the same work?
877 064e5e17cd928d8b7160dffc1
64e5e17cd928d8b7160dffc1- 18false
- 26false
- 310true
- 49false
- 5None of thesefalse
- Show AnswerHide Answer
- Workspace
- SingleChoice
Answer : 3. "10"
Q:Answer the following questions
A, B and C gets a total wage of Rs.3600 if they work together. A and B gets a total wage of Rs. 2800 if they work together and A alone gets Rs.1600. Find the efficiency ratio of A, B and C
877 063bd584a3d35cd0deed5cbe8
63bd584a3d35cd0deed5cbe8- 11:2:3false
- 22:4:3false
- 34:3:2true
- 42:5:4false
- Show AnswerHide Answer
- Workspace
- SingleChoice
Answer : 3. "4:3:2"
Q: A work could be completed in 100 days by some workers. How- ever, due to the absence of 10 workers, it was completed in 110 days. The original number of workers was:
870 06401e2ea86fd4161466d6a1c
6401e2ea86fd4161466d6a1c- 1100false
- 2110true
- 3180false
- 4144false
- Show AnswerHide Answer
- Workspace
- SingleChoice