8 Q: A and B together can plough a field in 10 hours but by himself A requires 15 hours. How long would B take to plough the same field?
2711 05ed7404322579c39005076a7
5ed7404322579c39005076a7- 110 hoursfalse
- 220 hoursfalse
- 330 hourstrue
- 440 hoursfalse
- Show AnswerHide Answer
- Workspace
- SingleChoice
Answer : 3. "30 hours"
Q: A and B can separately complete a piece of work in 20 days and 30 days respectively. They worked together for some time then B left the work. If A completed the rest of the work in 10 days, then B worked for how many days?
2710 05ecc965b372a1f6474abe759
5ecc965b372a1f6474abe759- 16 daystrue
- 28 daysfalse
- 312 daysfalse
- 416 daysfalse
- Show AnswerHide Answer
- Workspace
- SingleChoice
Answer : 1. "6 days"
Q: 120 men consume 720 kg of rice in 30 days. In how many days can 90 men consume 270 kg?
2642 060c098dec197293a4827316a
60c098dec197293a4827316a- 118false
- 212false
- 39false
- 415true
- Show AnswerHide Answer
- Workspace
- SingleChoice
Answer : 4. "15"
Q: A goldsmith observes that one of his employees prepares a necklace in 9 hours, while another employee prepares it in 10 hours. If they work together, they stud 10 gems less every hour and thus prepare a necklace in 5 hours, then the number of gems studded in each necklace is:
2559 0614c6e554d59797c590e5ca0
614c6e554d59797c590e5ca0- 11200false
- 21000false
- 3800false
- 4900true
- Show AnswerHide Answer
- Workspace
- SingleChoice
Answer : 4. "900 "
Q: Either 8 men or 17 women can paint a house in 33 days. The number of days required to paint three such houses by 12 men and 24 women working at the same rate is:
2536 05e86cfa0b22d214bc7c92e78
5e86cfa0b22d214bc7c92e78- 144false
- 243false
- 334true
- 466false
- Show AnswerHide Answer
- Workspace
- SingleChoice
Answer : 3. "34 "
Q: Anil, Deepak, and Dinesh together can complete a work in 35 days. Anil and Dinesh together can complete the same work in 60 days. In how many days Deepak alone can complete the same work?
2481 0610c6931997056628331c533
610c6931997056628331c533- 1105 daysfalse
- 284 daystrue
- 396 daysfalse
- 4110 daysfalse
- Show AnswerHide Answer
- Workspace
- SingleChoice
Answer : 2. "84 days"
Q: A and B can do a piece of work in 20 days and 30 days respectively. They started the work together but after 8 days they doing work in alternate days, started with B. how many days the work will be completed?
2417 05e9da3acef7e02504892dc5a
5e9da3acef7e02504892dc5a- 120false
- 212false
- 314false
- 416true
- 58false
- Show AnswerHide Answer
- Workspace
- SingleChoice
Answer : 4. "16 "
Q: Vinit and Gopal can do a work together in 4 days. Shyam and Mohan can do the same work in 12 days. So, in how many days can all four complete that work together?
2377 05f97f943d433054b5c8ad586
5f97f943d433054b5c8ad586- 14 daysfalse
- 23 daystrue
- 38 daysfalse
- 412 daysfalse
- Show AnswerHide Answer
- Workspace
- SingleChoice