Time and work Practice Question and Answer
8 Q: 6 carpenters make 96 windows in 16 days. If 8 carpenters work for 4 days how many windows will they make?
1859 0607d2f9eefac5e514ca9517f
607d2f9eefac5e514ca9517f- 116false
- 228false
- 336false
- 432true
- Show AnswerHide Answer
- Workspace
- SingleChoice
Answer : 4. "32"
Q: Tapas works twice as fast as Mihir. If both of them together complete a work in 12 days, Tapas alone can complete it in
1853 05e2061057925ca44aa9f2742
5e2061057925ca44aa9f2742- 115 daysfalse
- 218 daystrue
- 320 daysfalse
- 424 daysfalse
- Show AnswerHide Answer
- Workspace
- SingleChoice
Answer : 2. "18 days "
Q: G and H can do a work in 30 days. If H alone can do it in 50 days, then G alone can do it in__ days.
1851 05edf1e6aca41b347ed2fa6d5
5edf1e6aca41b347ed2fa6d5- 175true
- 270false
- 360false
- 464false
- Show AnswerHide Answer
- Workspace
- SingleChoice
Answer : 1. "75"
Q: Aarif, Arun and Abraham can do a work in 12, 20 and 24 days, respectively. They all begin together. Aarif leaves the work 1 day, Arun 3 days and Abraham 4 days before its completion. In how many days is the work finished?
1847 064871f2ee8d2170cb3a22a8f
64871f2ee8d2170cb3a22a8f- 111false
- 210false
- 38true
- 49false
- Show AnswerHide Answer
- Workspace
- SingleChoice
Answer : 3. "8"
Q: If p men working p hours per day for p days produce p units of work, then the units of work produced by n men working n hours a day for n days is
1830 05dd625b5a1c5834595c3b0bf
5dd625b5a1c5834595c3b0bf- 1$${p^2}\over {n^2} $$false
- 2$${p^3}\over {n^2} $$false
- 3$${n^2}\over {p^2} $$false
- 4$${n^3}\over {p^2} $$true
- Show AnswerHide Answer
- Workspace
- SingleChoice
Answer : 4. "$${n^3}\over {p^2} $$"
Q: Rajesh can do a work in 6 days and Vikram can do the same work in 5 days. The contract for the work is of Rs. 3300 . How much shall Vikram get if both of them work together?
1815 05f0ec09bb6738d790d138fc4
5f0ec09bb6738d790d138fc4- 1Rs.1800true
- 2Rs.1500false
- 3Rs.2000false
- 4Rs.1200false
- Show AnswerHide Answer
- Workspace
- SingleChoice
Answer : 1. "Rs.1800"
Q: P, Q and R can finish a work in 5 days, 10 days, and 15 days, respectively, working alone. P and Q works on first day, P and R works on second day and P and Q works on third day and son on till the work is completed. In how many days the work will be completed?
1798 064b4f877e154aff533729d6a
64b4f877e154aff533729d6a- 1$${13\over 2}$$false
- 2$${9\over 2}$$false
- 3$${7\over 2}$$true
- 4$${5\over 2}$$false
- Show AnswerHide Answer
- Workspace
- SingleChoice
Answer : 3. "$${7\over 2}$$"
Q: A particular job can be completed by a team of 10 men in 12 days, The same job can be completed by a team of 10 women in 6 days. How many days are needed to complete the job if the two teams work together?
1792 05ee1fc042bf4c4044646ad10
5ee1fc042bf4c4044646ad10- 14 daystrue
- 26 daysfalse
- 39 daysfalse
- 418 daysfalse
- Show AnswerHide Answer
- Workspace
- SingleChoice