Time and work Practice Question and Answer

  • Show AnswerHide Answer
  • Workspace

Answer : 4. "35 days"

Q:

Total wages of 6 men, 4 women and 8 boys are Rs 26. If the wages of 6 men is equal to that of 8 women and the wages of 4 women is equal to that of 6 boys, then find out the total wages of 8 men, 6 women and 4 days? 

12874 0

  • 1
    Rs. 25
    Correct
    Wrong
  • 2
    Rs. 29
    Correct
    Wrong
  • 3
    Rs. 32
    Correct
    Wrong
  • 4
    Rs. 24
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 2. "Rs. 29"

Q:

A, B and C together earn Rs. 2700 in 18 days. A and C together earn Rs. 940 in 10 days. B and C together earn Rs. 1520 in 20 days. Find the daily earning of C.

5975 0

  • 1
    Rs. 10
    Correct
    Wrong
  • 2
    Rs. 40
    Correct
    Wrong
  • 3
    Rs. 20
    Correct
    Wrong
  • 4
    Rs. 15
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 3. "Rs. 20"

  • Show AnswerHide Answer
  • Workspace

Answer : 2. "42"

Q: 30 Men contracts to complete a work in 50 days. But after 25 days, it is come to know that only 1/3rd of the work has been done. How many more workers are required to complete the work in time? 4570 2

  • 1
    25
    Correct
    Wrong
  • 2
    30
    Correct
    Wrong
  • 3
    35
    Correct
    Wrong
  • 4
    40
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 2. "30"

Q: A single person takes 4 minutes to type a page, if from 12 noon to 1.00 pm., 1080 pages are to be typed, how many persons should be employed on this job? 4204 0

  • 1
    108
    Correct
    Wrong
  • 2
    60
    Correct
    Wrong
  • 3
    90
    Correct
    Wrong
  • 4
    72
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 4. "72"

Q: 30 Men can complete a work in 25 days. In how many days can 75 men complete it? 4189 2

  • 1
    15
    Correct
    Wrong
  • 2
    12
    Correct
    Wrong
  • 3
    16
    Correct
    Wrong
  • 4
    10
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 4. "10"

Q: Amar can complete ¼ work in 3 days and Bhaskar can complete 1/6 th of the work in 4 days. If they work on it together, they get Rs 1800. Find the amount received by Amar. 3882 1

  • 1
    Rs 600
    Correct
    Wrong
  • 2
    Rs 1000
    Correct
    Wrong
  • 3
    Rs 1080
    Correct
    Wrong
  • 4
    Rs 1200
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 4. "Rs 1200"

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error