Join Examsbook
685 0

Q:

24 women take 14 days to complete a piece of work which can be completed by 14 men in 12 days. 18 men started working and after 5 days, 10 men left and 8 women joined them. How many days will it take them to complete the remaining work?

  • 1
    14 days
  • 2
    5 days
  • 3
    $$ {9{1\over2}}{days}$$
  • 4
    $$ {6{1\over2}}{days}$$
  • 5
    $$ {8{1\over2}}{days}$$
  • Show AnswerHide Answer
  • Workspace

Answer : 4. "$$ {6{1\over2}}{days}$$"

Are you sure

  Report Error

Please Enter Message
Error Reported Successfully