A, B , C can finish a work in 10, 12, and 15 days respectively. They start working together. If B stops after 2 days, how long would it take A and C to finish the remaining work
5Q:
A, B , C can finish a work in 10, 12, and 15 days respectively. They start working together. If B stops after 2 days, how long would it take A and C to finish the remaining work
- 13 daystrue