Join Examsbook
467 0

Q:

Ajay. Vijay and Sashi can do a piece of work in 20, 40 and 60 days, respectively. In how many days can Ajay do the work if he is assisted by Vijay and Sashi on every fourth day?

  • 1
    15 days
  • 2
    $${{150\over3}}$$ days
  • 3
    12 days
  • 4
    $${{44\over3}}$$ days
  • Show AnswerHide Answer
  • Workspace

Answer : 2. "$${{150\over3}}$$ days"

Are you sure

  Report Error

Please Enter Message
Error Reported Successfully