Join Examsbook
252 0

Q:

 ‘A’ can complete a work in 20 days while B is 25% more efficient than ‘A’. B worked for 6 days and left, the remaining work is completed by ‘C’ in 15 days. Find how many days ‘C’ can complete the whole work alone. 

  • 1
    27 days
  • 2
    21 days
  • 3
    18 days
  • 4
    24 days
  • 5
    30 days
  • Show AnswerHide Answer
  • Workspace

Answer : 4. "24 days"

Are you sure

  Report Error

Please Enter Message
Error Reported Successfully