8Q: Project Time Management - Processes Describe the Inputs, Tools and Techniques, Outputs of Activity Duration Estimating ? 583 05b5cc7eae4d2b41977751af6
5b5cc7eae4d2b41977751af6- Show AnswerHide Answer
- Workspace
- SingleChoice
Answer :
Explanation :
I. Inputs Enterprise environmental factors Organizational process assets Project scope statement Activity list Activity attributes Activity resource requirements Resource calendars Project management plan - Risk register - Activity cost estimates II. Tools and Techniques Expert judgment Analogous estimating Parametric estimating Three-point estimates Reserve analysis III. Outputs Activity duration estimates Activity attributes (updates)
Q: Project Time Management - Processes Describe the Inputs, Tools and Techniques, Outputs of Schedule Development? 1055 05b5cc7eae4d2b41977751af5
5b5cc7eae4d2b41977751af5- Show AnswerHide Answer
- Workspace
- SingleChoice
Answer :
Explanation :
I. Inputs Organizational process assets Project scope statement Activity list Activity attributes Project schedule network diagrams Activity resource requirements Resource calendars Activity duration estimates Project management plan - RisK register II. Tools and Techniques Schedule network analysis Critical path method Schedule compression What-if scenario analysis Resource leveling Critical chain method Project management software Applying calendars Adjusting leads and lags Schedule model III. Outputs Project schedule Schedule model data Schedule baseline Resource requirements (updates) Activity attributes (updates) Project calendar (updates) Requested changes Project management plan (updates) - Schedule management plan(updates)
Q: Project Time Management - Processes Describe the Inputs, Tools and Techniques, Outputs of Schedule Control ? 813 05b5cc7eae4d2b41977751af4
5b5cc7eae4d2b41977751af4- Show AnswerHide Answer
- Workspace
- SingleChoice
Answer :
Explanation :
I. Inputs Schedule management plan Schedule baseline Performance reports Approved change requests II. Tools and Techniques Progress reporting Schedule change control system Performance measurement Project management software Variance analysis Schedule comparision bar charts III. Outputs Schedule model data (updates) Schedule baseline (updates) Performance measurements Requested changes Recommended corrective actions Organizational process assets (updates) Activity list (updates) Activity attributes (updates) Project management plan (updates)
Q: Project Cost Management What are the Project Management Processes included in the Project Cost Management? 673 05b5cc7eae4d2b41977751af3
5b5cc7eae4d2b41977751af3- Show AnswerHide Answer
- Workspace
- SingleChoice
Answer :
Explanation :
Cost Estimating - Developing an approximation of the costs of the resources needed to complete project activities. Cost Budgeting - Aggregating the estimated costs of individual activities or work packages to establish a cost baseline Cost Control - Influencing the factors that create cost variances and controlling changes to the project budget.
Q: Project Cost Management - Processes Describe the Inputs, Tools and Techniques , Outputs included in the Cost Estimating ? 636 05b5cc7eae4d2b41977751af2
5b5cc7eae4d2b41977751af2- Show AnswerHide Answer
- Workspace
- SingleChoice
Answer :
Explanation :
I. Inputs Enterprise environmental factors Organizational process assets Project scope statement Work breakdown structure WBS dictionary Project management plan - Schedule management plan - Staffing management plan - Risk register II. Tools and Techniques Analogous estimating Determine resource cost rates Bottom-up estimating Parametric estimating Project management software Vendor bid analysis Reserve analysis Cost of quality III. Outputs Activity cost estimates Activity cost estimate supporting detail Requested changes Cost management plan (updates)
Q: Project Cost Management - Processes Describe the Inputs, Tools and Techniques , Outputs included in the Cost Budgeting ? 1012 05b5cc7eae4d2b41977751af1
5b5cc7eae4d2b41977751af1- Show AnswerHide Answer
- Workspace
- SingleChoice
Answer :
Explanation :
I. Inputs Project scope statement Work breakdown structure WBS dictionary Activity cost estimates Activity cost estimate supporting detail Project schedule Resource calendars Contract Cost management plan II. Tools and Techniques Cost aggregation Reserve analysis Parametric estimating Funding limit reconciliation III. Outputs Cost baseline Project funding requirements Cost management plan (updates) Requested changes
Q: Project Cost Management - Processes Describe the Inputs, Tools and Techniques , Outputs included in the Cost Control ? 927 05b5cc7eae4d2b41977751af0
5b5cc7eae4d2b41977751af0- Show AnswerHide Answer
- Workspace
- SingleChoice
Answer :
Explanation :
I. Inputs Cost baseline Project funding requirements performance reports Work performance information Approved change requests Project management plan II. Tools and Techniques Cost change control system Performance measurement analysis Forecasting Project performance reviews Project management software Variance management III. Outputs Cost estimate (updates) Cost baseline (updates) Performance measurements Forecasted completion Requested changes Recommended corrective actions Organizational process assets (updates) Project management plan (updates)
Q: Project Quality Management What are the Project Management Processes included in the Project Quality Management? 749 05b5cc7eae4d2b41977751aef
5b5cc7eae4d2b41977751aef- Show AnswerHide Answer
- Workspace
- SingleChoice
Answer :
Explanation :
Quality planning - Identifying which quality standards are relevant to the project and determining how to satisfy them Perform Quality Assurance - Applying the planned , systematic quality activities to ensure that the project employs all processes needed to meet requirements. Perform Quality Control - monitoring specific project results to determine whether they comply with relevant quality standards and identifying ways to eliminate causes of unsatisfactory performance.