Tarun and Uday together can complete a piece of work in 16 days; Uday and Vivek together can complete the work in 28 4/5 days; while Tarun and Vivek together can complete the work in 18 days. In how many days can Tarun alone complete the work?

  • 1
    18 days
  • 2
    24 days
  • 3
    30 days
  • 4
    36 days
  • 5
    None of these
  • Show AnswerHide Answer
  • Workspace

Answer : 2. "24 days "