Aptitude Practice Question and Answer

Q:

A particular job can be completed by a team of 10 men in 12 days, The same job can be completed by a team of 10 women in 6 days. How many days are needed to complete the job if the two teams work together?

1909 0

  • 1
    4 days
    Correct
    Wrong
  • 2
    6 days
    Correct
    Wrong
  • 3
    9 days
    Correct
    Wrong
  • 4
    18 days
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 1. "4 days "

Q:

If a sum of money becomes 8 times in 9 years at compound interest annually, in how much time it will become 32 times?

1909 0

  • 1
    15 year
    Correct
    Wrong
  • 2
    20 year
    Correct
    Wrong
  • 3
    25 year
    Correct
    Wrong
  • 4
    None of these
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 4. "None of these"

Q:

A work could be completed in 100 days by some workers. However, due to the absence of 10 workers, it was completed in 110 days. The original number of workers was

1909 0

  • 1
    100
    Correct
    Wrong
  • 2
    110
    Correct
    Wrong
  • 3
    55
    Correct
    Wrong
  • 4
    50
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 2. "110"

Q:

The value of  $${cosec^2} 18° -{1\over cot^272°}$$.

1909 0

  • 1
    $${1 \over \sqrt { 3}}$$
    Correct
    Wrong
  • 2
    $$ \sqrt2\over {3 } $$
    Correct
    Wrong
  • 3
    $${1\over2} $$
    Correct
    Wrong
  • 4
    1
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 4. "1"

Q:

If ( 2x – y): ( 5x+3y)=3 : 8 then ( x2 + y2) : ( x2 – y2)=?

1907 0

  • 1
    257 : 255
    Correct
    Wrong
  • 2
    145 : 144
    Correct
    Wrong
  • 3
    144 : 143
    Correct
    Wrong
  • 4
    133 : 122
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 2. "145 : 144"

Q: The average value found for 20 observations was 75. It was noticed later that 97 was read as 79. So, what was the correct average value? 1907 0

  • 1
    75.7
    Correct
    Wrong
  • 2
    75.8
    Correct
    Wrong
  • 3
    75.9
    Correct
    Wrong
  • 4
    75.6
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 3. "75.9"
Explanation :

undefined

Q:

A tank is 25m long 12m wide and 6m deep. The cost of plastering its walls and bottom at 225 paise per sq m is

1906 0

  • 1
    Rs. 1674
    Correct
    Wrong
  • 2
    Rs. 1540
    Correct
    Wrong
  • 3
    Rs. 1632
    Correct
    Wrong
  • 4
    Rs. 1600
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 1. "Rs. 1674 "

Q:

Mohit borrowed Rs. 22000 at 5% simple interest repayable in 5 equal installments. What will be the annual installment payable by him?

1906 0

  • 1
    Rs 4800
    Correct
    Wrong
  • 2
    Rs 5500
    Correct
    Wrong
  • 3
    Rs 4600
    Correct
    Wrong
  • 4
    Rs 500
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 3. "Rs 4600"

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully