Time and work Practice Question and Answer

Q:

A and B under took a work Rs 2200. A alone can do the work in 10 days and B alone can do the work in 12 days. If they work together, then what will be the difference (in Rs) in the amount they receive?  

1658 0

  • 1
    350
    Correct
    Wrong
  • 2
    250
    Correct
    Wrong
  • 3
    200
    Correct
    Wrong
  • 4
    300
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 3. "200"

Q:

A job can be completed by 12 men in 12 days. How many extra days will be needed to complete the job if 6. men leave after working for 6 days? 

1656 0

  • 1
    12 days
    Correct
    Wrong
  • 2
    24 days
    Correct
    Wrong
  • 3
    3 days
    Correct
    Wrong
  • 4
    6 days
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 4. "6 days "

Q:

The ratio of Ram, Shyam, and Mohan's Working speed is 2: 3: 5 if they get Rs 40,000 for some work. Then find the share of Shyam(in Rupees)?

1654 0

  • 1
    12,000
    Correct
    Wrong
  • 2
    20,000
    Correct
    Wrong
  • 3
    8,0000
    Correct
    Wrong
  • 4
    15,000
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 2. "20,000"

Q:

5 men can do a piece of work in 6 days while 10 women can do it in 5 days. In how many days can 5 women and 3 men do it? 

1640 0

  • 1
    4 days
    Correct
    Wrong
  • 2
    5 days
    Correct
    Wrong
  • 3
    6 days
    Correct
    Wrong
  • 4
    8 days
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 2. "5 days "

Q:

To do a certain work, the ratio of the efficiencies of X and Y is 5:4. Working together, they can complete the same work in 10 days. Y alone starts the work and leaves after 5 days. The remaining work will be completed by X alone in:

1621 1

  • 1
    14 days
    Correct
    Wrong
  • 2
    12 days
    Correct
    Wrong
  • 3
    10 days
    Correct
    Wrong
  • 4
    15 days
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 1. "14 days "

Q: A, B and C can complete a piece of work in 24, 6 and 12 days respectively. Working together, they will complete the same work in 1602 0

  • 1
    $${1\over 4}days$$
    Correct
    Wrong
  • 2
    $${7\over 24}days$$
    Correct
    Wrong
  • 3
    $$3{3\over 7}days$$
    Correct
    Wrong
  • 4
    $$4 \ days$$
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 3. " $$3{3\over 7}days$$"

Q: A can do a piece of work in 4 hours; B and C can do it in 3 hours. A and C can do it in 2 hours. How long will B alone take to do it ? 1600 0

  • 1
    10 hours
    Correct
    Wrong
  • 2
    12 hours
    Correct
    Wrong
  • 3
    8 hours
    Correct
    Wrong
  • 4
    24 hours
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 2. " 12 hours"

Q: A can do a piece of work in 15 days and B in 20 days. If they together work it for 4 days, then the fraction of the work that is left is: 1595 0

  • 1
    $${8\over 15}$$
    Correct
    Wrong
  • 2
    $${7\over 15}$$
    Correct
    Wrong
  • 3
    $${1\over 4}$$
    Correct
    Wrong
  • 4
    $${1\over 10}$$
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 1. "$${8\over 15}$$"

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully