Time and work Practice Question and Answer
8 4 4 Q:
5dd62ac4c2282c484e4b3a66 4 4 4 4 4 Q:
5d71f0d9e70d464ce7165103 4 Q:
5e8ff0a061b7c13fb88fcb81
Q: A can do a piece of work in 4 hours; B and C can do it in 3 hours. A and C can do it in 2 hours. How long will B alone take to do it ? 1600 05cf0f481c97a225730e3b267
5cf0f481c97a225730e3b267- 110 hoursfalse
- 212 hourstrue
- 38 hoursfalse
- 424 hoursfalse
- Show AnswerHide Answer
- Workspace
- SingleChoice
Answer : 2. " 12 hours"
Q: 40 men can complete a piece of work in 40 days. They started the work together. But at the end of each 10th day, 5 men left the job. The work would have been completed in
1427 05dd62ac4c2282c484e4b3a66
5dd62ac4c2282c484e4b3a66- 1$$ 56{2\over 3} days $$true
- 2$$ 53{1\over 3} days $$false
- 352 daysfalse
- 450 daysfalse
- Show AnswerHide Answer
- Workspace
- SingleChoice
Answer : 1. "$$ 56{2\over 3} days $$"
Q: A can do a piece of work in 6 days and B in 9 days. How many days will both take together to complete the work? 1738 05cf0eadb0b8bee0fb6178aca
5cf0eadb0b8bee0fb6178aca- 17.5 daysfalse
- 25.4 daysfalse
- 33.6 daystrue
- 43 daysfalse
- Show AnswerHide Answer
- Workspace
- SingleChoice
Answer : 3. " 3.6 days"
Q: A can cultivate $${2\over 5}$$ of a land in 6 days and b can cultivate $${1\over 6}$$ of the same land in 10 days. Working together A and B can cultivate $${4\over 5}$$ of the land in; 1777 05cf0ec53c97a225730e3b246
5cf0ec53c97a225730e3b246- 14 daysfalse
- 25 daysfalse
- 38 daystrue
- 410 daysfalse
- Show AnswerHide Answer
- Workspace
- SingleChoice
Answer : 3. " 8 days"
Q: A and B can do a piece of work in 72 days. B and C can do it in 120 days. A and C can do it in 90 days. In how many days all three together can do the work ? 1698 05cf0f244c97a225730e3b25d
5cf0f244c97a225730e3b25d- 180 daysfalse
- 2100 daysfalse
- 360 daystrue
- 4150 daysfalse
- Show AnswerHide Answer
- Workspace
- SingleChoice
Answer : 3. " 60 days"
Q: A, B and C can complete a work in 10, 15 and 20 days respectively. A and B start it together. B is replaced by C after 2 days. A leave it after one more day. In how many days work was completed? 3027 05d1485969aeb0a08f1e67225
5d1485969aeb0a08f1e67225- 113false
- 2\(13 {1 \over 13 }\)true
- 3\(18 {4 \over 3 }\)false
- 418false
- Show AnswerHide Answer
- Workspace
- SingleChoice
Answer : 2. " \(13 {1 \over 13 }\)"
Q: A, B and C can complete a piece of work in 10, 12, and 15 days respectively, They started the work together. But A left the work before 5 days of its completion. B also left the work 2 days after A left. In how many days was the work completed?
1524 05d71f0d9e70d464ce7165103
5d71f0d9e70d464ce7165103- 14 daysfalse
- 25 daysfalse
- 37 daystrue
- 48 daysfalse
- Show AnswerHide Answer
- Workspace
- SingleChoice
Answer : 3. "7 days"
Q: A and B together can do a piece of work in 12 days which B and C together can do in 16 days. After A has been working at it for 5 days and B for 19 days, C finishes it in 7 days. In how many days B could finish the whole work?
1674 05e8ff0a061b7c13fb88fcb81
5e8ff0a061b7c13fb88fcb81- 148 daystrue
- 224 daysfalse
- 316 daysfalse
- 412 dayfalse
- Show AnswerHide Answer
- Workspace
- SingleChoice
Answer : 1. "48 days "
en29211rated