Time and work Practice Question and Answer
8 Q: 30 persons can do a piece of work in 24 days. How many more people are required to complete the work in 20 days?
1075 06095279b0b74c22fcbaab1e8
6095279b0b74c22fcbaab1e8- 14false
- 25false
- 36true
- 4None of thesefalse
- Show AnswerHide Answer
- Workspace
- SingleChoice
Answer : 3. "6"
Q: If 20 women can lay a road of length 100m in 10 days. 10 women can lay the same road of length 50m in:
1075 05f1a903464a4af41892850a1
5f1a903464a4af41892850a1- 110 daytrue
- 220 dayfalse
- 35 dayfalse
- 415 dayfalse
- Show AnswerHide Answer
- Workspace
- SingleChoice
Answer : 1. "10 day"
Q: A and B can do a work in 18 and 24 days respectively. They worked together for 8 days and then A left. The remaining work was finished by B in
1067 05ec5f083980ff60a66c356f2
5ec5f083980ff60a66c356f2- 15 daysfalse
- 2$$ 5{1\over3}$$ daystrue
- 38 daysfalse
- 410 daysfalse
- Show AnswerHide Answer
- Workspace
- SingleChoice
Answer : 2. "$$ 5{1\over3}$$ days"
Q: 16 boys or 12 women can do a piece of work in 28 days. In how many days will the same work be done by 4 boys and 4 women, if they all work together?
1066 06433d81c1ce944a93e967955
6433d81c1ce944a93e967955- 136 daysfalse
- 248 daystrue
- 344 daysfalse
- 440 daysfalse
- Show AnswerHide Answer
- Workspace
- SingleChoice
Answer : 2. "48 days"
Q: 24 women take 14 days to complete a piece of work which can be completed by 14 men in 12 days. 18 men started working and after 5 days, 10 men left and 8 women joined them. How many days will it take them to complete the remaining work?
1063 061c3423e64388627a24daa9c
61c3423e64388627a24daa9c- 114 daysfalse
- 25 daysfalse
- 3$$ {9{1\over2}}{days}$$false
- 4$$ {6{1\over2}}{days}$$true
- 5$$ {8{1\over2}}{days}$$false
- Show AnswerHide Answer
- Workspace
- SingleChoice
Answer : 4. "$$ {6{1\over2}}{days}$$"
Q: P can do a task in 30 days, Q is 50% more efficient than P, R can do the same work in 10 days less than Q if R and Q start task together and after X days they left the task and P completed the remaining task in (X + 8) days. then find the value of X?
1052 064dcbde3d02c5c746bf5be90
64dcbde3d02c5c746bf5be90- 12false
- 24true
- 35false
- 48false
- 56false
- Show AnswerHide Answer
- Workspace
- SingleChoice
Answer : 2. "4"
Q: A, B and three men can finish a work in 10, 20 and 15 days respectively, then in how many days will all three together finish the work?
1048 0631094a3d9ac741324b7ec3d
631094a3d9ac741324b7ec3d- 17/28false
- 260/16false
- 313/60true
- 419/60false
- Show AnswerHide Answer
- Workspace
- SingleChoice
Answer : 3. "13/60"
Q: Time taken to travel a certain distance of ‘x’ km at speed of 40 km/h is 2 hours more than the time taken to travel (x+20) km at speed of 60km/h. Find the time taken to travel (x+40) km at the speed of 40 km/h?
1047 060408dd8b0e8d85dadab87dc
60408dd8b0e8d85dadab87dc- 19 hoursfalse
- 25 hoursfalse
- 38 hourstrue
- 46 hoursfalse
- 57.5 hoursfalse
- Show AnswerHide Answer
- Workspace
- SingleChoice