Join Examsbook
1439 0

Q: P, Q, and R can do a job in 12 days together.  If their efficiency of working be in the ratio 3 : 8 : 5, Find in what time Q can complete the same work alone?

  • 1
    36 days
  • 2
    30 days
  • 3
    24 days
  • 4
    22 days
  • Show AnswerHide Answer
  • Workspace

Answer : 1. "36 days"
Explanation :

Answer: A) 36 days Explanation: Given the ratio of efficiencies of P, Q & R are 3 : 8 : 5 Let the efficiencies of P, Q & R be 3x, 8x and 5x respectively They can do work for 12 days. => Total work = 12 x 16x = 192x   Now, the required time taken by Q to complete the job alone = 162x8x = 24 days.

Are you sure

  Report Error

Please Enter Message
Error Reported Successfully